During a project walkthrough near completion, what type of list is created to address remaining details?

Completion List

Action List

Punch List

The correct answer is the punch list. A punch list is a document created towards the end of a construction project to identify work that is incomplete or requires correction before final payment can be made. It typically includes a detailed list of tasks or items that need to be addressed, which may encompass minor repairs, touch-ups, or issues that did not meet the project specifications. The punch list serves as a clear communication tool between the contractor and the client, ensuring that both parties are aware of outstanding items that need to be resolved to consider the project complete.

In contrast, a completion list or final list might generally suggest a summary of all the completed tasks, rather than highlighting the remaining issues that need attention. Similarly, while an action list could imply tasks needing execution, it does not specifically focus on the particular context of finishing touches or final corrections necessary for project closure, which is the primary purpose of a punch list.

Final List

Next

Report this question